Sydney Opera House Project-Masterpiece And A Strong Case For Project Management Failure!

Sydney Opera House Project-Masterpiece And A Strong Case For Project Management Failure!

Share this page

The Sydney Opera House project serves as a clear example of the importance of effective project management practices. The project’s difficulties, including cost overruns, delays, and design changes, can be attributed in large part to poor management practices. The lack of clear project goals, poor communication, inadequate planning, insufficient budget, lack of oversight, and lack of experienced team members all contributed to the project’s difficulties.

Additionally, the lack of risk management, change management, and project management practices led to a lack of control over the project, which ultimately made it more difficult to deliver the final product on time and within budget.

There were several failure metrics that could be used to evaluate the Sydney Opera House project, including:

  1. Cost: The project’s initial budget was $7 million, but the final cost was over $100 million, which represents a significant cost overrun.
  2. Schedule: The project faced delays and was not completed on time.
  3. Quality: The final product did not meet the original design specifications, and there were numerous design changes made during the construction process.
  4. Scope: The scope of the project was not clearly defined, and the architects and the government had different ideas about what the final product should look like.
  5. Risk: The project team did not conduct a thorough risk assessment at the beginning of the project, which would have helped identify potential issues and develop plans to mitigate them.
  6. Performance: The project team was not experienced enough to handle the complexity of this project, which led to construction difficulties.
  7. Customer satisfaction: The client, the government, was not satisfied with the final product, which was not meeting the original design.
  8. Return on Investment: the project was not able to deliver the return on investment as was expected, which was a major failure metric for the project.
Inside the hall from https://www.abc.net.au/

The poor management practices that contributed to the difficulties faced by the Sydney Opera House project included:

  1. Lack of clear project goals: The scope of the project was not clearly defined and the architects and the government had different ideas about what the final product should look like.
  2. Poor communication: There was a lack of communication between the architects, the government, and the construction team, which led to delays and misunderstandings.
  3. Inadequate planning: The project was not adequately planned, which led to cost overruns and delays in construction.
  4. Insufficient budget: The initial budget was not sufficient to cover the cost of construction, which led to additional costs being added to the project.
  5. Lack of oversight: There was a lack of oversight and accountability, which allowed problems to go unchecked and led to further delays and additional costs.
  6. Inexperience: The project team was not experienced enough to handle the complexity of this project, which led to construction difficulties.
  7. Inadequate project management: There was poor management of the project, which led to delays, cost overruns, and the final product not meeting the original design.
  8. Political interference: The government’s interference in the design and construction process added to the delays and increased costs
From the lobby from https://www.abc.net.au/

The risk management in the Sydney Opera House project was inadequate as well and likely contributed to the project’s difficulties. Some of the specific issues with risk management on the project include:

  1. Lack of risk assessment: The project team did not conduct a thorough risk assessment at the beginning of the project, which would have helped identify potential issues and develop plans to mitigate them.
  2. No contingency plan: There was no contingency plan in place to address potential issues that arose during the project, which left the team ill-prepared to handle unexpected problems.
  3. Inadequate cost estimates: The initial budget was not realistic, and the cost estimates for the project were inadequate, which led to significant cost overruns.
  4. Lack of monitoring and control: There was a lack of monitoring and control over the project, which allowed risks to go unchecked and led to further delays and additional costs.
  5. Insufficient communication: There was a lack of communication between the architects, the government, and the construction team, which led to delays and misunderstandings.
  6. No change management process: The project team did not have a change management process in place, which made it difficult to handle design changes and led to additional costs and delays.
  7. No project management: The project management practices were inadequate, which led to delays, cost overruns, and the final product not meeting the original design.
The Opera House was under construction in 1965. Image: Max Dupain, State Library of NSW

Overall, the Sydney Opera House project serves as a clear reminder of the importance of effective project management practices in ensuring that a project is completed on time, within budget, and to the satisfaction of the client. It also highlights the importance of having a clear project management plan, a realistic budget, and a clear change management process.

We at Phi Contracting Co realized that importance, and we applied all the project management practices in all our projects, contact us by visiting our website: https://phicontracting.net/ to see how we helped others in delivering their projects successfully.